Project source | MC-SM-01 |
---|---|
Risk Category | It may be too much change for the organization |
Risk Event | Organization may resist supporting this initiative |
Initiative Size | $2 million to $10 million |
Industry | IT (Information Technology solutions) |
Foreseen? | No |
Response Selected | Accept by default - risk or response was not considered |
Planned Response | No response actions were planned |
Risk Monitoring | There was no monitoring plan |
Risk Occurred ? | Yes |
Risk Event Outcome | Meetings with implementing organization were poorly attended or did not occur, delaying completion of the work and minimizing buy-in. |
Pct actual cost impact | 10 |
Pct schedule lmpact | 20 |