Project sourceMC-SM-01
Risk CategoryIt may be too much change for the organization
Risk EventOrganization may resist supporting this initiative
Initiative Size$2 million to $10 million
IndustryIT (Information Technology solutions)
Foreseen?No
Response SelectedAccept by default - risk or response was not considered
Planned Response

No response actions were planned

Risk Monitoring

There was no monitoring plan

Risk Occurred ?Yes
Risk Event Outcome

Meetings with implementing organization were poorly attended or did not occur, delaying completion of the work and minimizing buy-in.
Early-phase deliverables were not used, reducing ability of project to get additional funding and making it difficult to extend the work beyond the pilot scope

Pct actual cost impact10
Pct schedule lmpact20