Read the entire entry – common access

Project sourceSSC-02
Risk CategoryWe may not have understood what we were getting into
Risk EventCustomer may not have enough demand to support product
Initiative Size$50,001 to $100,000
IndustryIT (Information Technology solutions)
Foreseen?Yes
Percent cost loading0
Pct schedule loading0
Response SelectedMitigate
Planned Response

Identify cyber partner roles and responsibilities in order to make criteria and needs very explicit

Plan Implemented?Yes
Risk Monitoring

There was no monitoring plan

Risk Occurred ?TBD (initiative not completed yet)