Project source | SSC-01 |
---|---|
Risk Category | We may not have understood what we were getting into |
Risk Event | We were unrealistic in our estimates of the cost |
Initiative Size | $2 million to $10 million |
Industry | IT (Information Technology solutions) |
Foreseen? | No |
Percent cost loading | 0 |
Pct schedule loading | 0 |
Response Selected | Accept by default - risk or response was not considered |
Planned Response | No response actions were planned |
Risk Monitoring | There was no monitoring plan |
Risk Occurred ? | TBD (initiative not completed yet) |